Hover or tap underlined Spanish terms to see their translation and exam tip.
Si un muelle de atraque es modificado considerablemente en longuitud por una obra portuaria, ¿qué haremos con el portulano?If a berthing quay is considerably changed in length by harbour works, what will we do with the harbour plan?
Show the answer
Correct answer: c) We will cut out the notice to mariners and stick it on our chart to update it, or buy a new one with the change.
Why it is correct
The notice to mariners gives the correction to stick on, or you buy an updated chart.
Why the others are not
- a) It must be corrected.
- b) The correction comes from the official notice.
- d) There are more options.
How to work it out in the exam
- Chart up to date: notices to mariners.
Where this question comes from
- Ministerio de Transportes (Madrid) · 2019 · Convocatoria de junio · PY Test 1 · question 21 Official paper · Official answer key
- Ministerio de Transportes (Madrid) · 2019 · Convocatoria de junio · PY Test 2 · question 27 Official paper · Official answer key
Try it: Navigation calculations
Pending instructor review. Machine translation, not reviewed.